Crane hand signals drill: see the signal, name the move

Look at a drawn hand signal and pick what it asks the operator to do. Every round covers all 19 signals in a new order, and learn mode lists each one with its meaning.

Method checked against OSHA 29 CFR 1926 Subpart CC, Appendix A on 21 Oct 2026. A recognition aid for study, not a substitute for the hand signal chart posted at your site or for a qualified signal person.

The 19 signals are the ones OSHA lists as the Standard Method for cranes and derricks in construction. The stick figures and the descriptions are our own; no OSHA or ASME figure is copied. Motion marks (arrows, chevrons and tap lines) are drawn in the accent color.

Original drawings · 19 signals

Crane hand signals drill

Each round shows every signal once, in a random order. Pick what the signal person is asking for, check your answer, and read why. Tab to the answer group and use the arrow keys to choose.

Order 20261021 · 0 of 19 answered · 0 correct

Signal 1 of 19

What does this hand signal mean?

When the Standard Method applies

Under 29 CFR 1926.1419, paragraph (c)(1), hand signals to a crane operator must follow the Standard Method in Appendix A. Other hand signals are allowed only where the Standard Method can't be used or doesn't cover an attachment operation. In that case paragraph (c)(2) has the signal person, the operator and the lift director (where there is one) meet before the operation and agree on the signals.

29 CFR 1926.1422 requires a hand signal chart to be posted on the equipment or in plain view near the hoisting work. A signal person who uses hand signals must know and understand the Standard Method, and shows it through an oral or written test and a practical test (29 CFR 1926.1428, paragraphs (c)(1) and (c)(5)).

Stop and emergency stop work differently from the rest. Under 29 CFR 1926.1419, paragraph (j), anyone who notices a safety problem uses the stop or emergency stop signal to warn the operator or signal person. A separate rule, 29 CFR 1926.1417, paragraph (y), puts the duty to obey that signal on the operator.

This drill follows OSHA's Appendix A only. ASME B30.5 is the consensus standard for mobile and locomotive cranes, cited here by number only; if your site or employer works to it, check your own copy for its signal chart.

Pairs that are easy to mix up

  • Raise boom or raise the boom and lower the load. Both have the arm out and the thumb up. The second adds fingers opening and closing for as long as the load should move. The same split applies to lower boom and lower the boom and raise the load, with the thumb down.
  • Hoist or lower. Both trace small circles. For hoist the forearm and finger point up; for lower they point down.
  • Extend or retract the telescoping boom. Both fists sit at the waist. Thumbs pointing away from each other mean extend; thumbs pointing at each other mean retract.
  • Stop or emergency stop. Stop swings one arm with the palm down; emergency stop swings both.
  • Swing or trolley travel. Swing points with the index finger. Trolley travel points with the thumb of a closed hand and jerks the hand sideways.
  • Crawler travel on both tracks or one track. For both tracks the two fists roll around each other in front of the body. For one track, one fist is held up on the side of the locked track while only the other fist rotates in front of the body.
  • Use main hoist or use auxiliary hoist. A tap on top of the head selects the main hoist; a tap on the elbow of an upright forearm selects the whipline. Either way, the normal motion signal follows.

The score is correct answers ÷ 19 × 100, rounded to a whole percent. It measures how well you recognize these drawings, not how you will do on any exam.

Related practice

Signals are one part of crane operations study. For the load chart side, work the load chart practice problems on invented charts. For the written exams as a whole, see the NCCCO written exam prep page.

Try one question

Question 1 of the free 10-question check on NCCCO written. No signup.

Question 1 of 10 · free checkUntimed

Operations

Which action creates side loading on a crane boom?

Published references

Checked 21 October 2026. Original drawings and descriptions; no regulation figures, standard text or exam items reproduced.

Preparing for the NCCCO written exams?

Use the free 10-question check to find topics that need more study.

Take the free 10-question NCCCO written check

By the Boom Angle editorial team. Report an error with the order seed and signal number.